project brief

underground conduit trench at commercial site Houston
HCA Hospital Power Conduit Upgrade

HCA Hospital

Running new primary conduit from the street vault to the main electrical room, then stubbing up, backfilling in controlled lifts and compacting to spec, all while the hospital stayed fully operational.

  • Achieve 95 %+ compaction on every backfill lift

  • Finish trench-to-panel pathway during off-peak hours

  • Keep critical-care power online with zero outages

the result

Conduit installed in three night shifts, inspections passed first time, and power remained uninterrupted throughout. Final density tests averaged 97 %, giving the owner a rock-solid duct bank for future growth.

recent projects

Delivering dependable underground utility solutions you can trust.