project brief

trench with conduit pipes ready for backfill Houston
industrial conduit service trenching Houston site

HCA Hospital

Preparing the electrical room by installing conduit stub-ups through the slab, then backfilling in 8-inch lifts with density testing to create a stable base for new switchgear.

  • Place every stub-up to exact plan coordinates

  • Achieve 95 % Proctor density on each lift

  • Complete work overnight to avoid hospital disruption

the result

Twenty-four stub-ups installed, laser-verified true; four lifts compacted to a 97 % average; room handed back dust-free six hours before morning rounds, keeping the switchgear schedule ahead of plan.